TECO F510 Inverter
Quick Start Guide
1) Ensure that the Inverter & the motor have the correct KW power and voltage
ratings.
Motor full load amps must not exceed the Inverter rating.
2) Ensure that the supply & Motor cables are connected correctly prior to
power up.
3) Connect supply cable to terminals R/L1, S/L2, T/L3
4) Connect motor cable to terminals U/T1, V/T2, W/T3
(Swap two leads if motor runs in reverse direction).
5) Connect supply Earth and the motor Earth to the drive Earth
terminal.
Note:-
I ) For detailed installation
and wiring refer to the
Instruction
manual.
This guide is to assist you in installing and running the inverter and verify that it is
functioning correctly for it’s main and basic features.
For detailed information and if there are any doubts please refer to the instruction manual.
Step 1
Supply & Motor connection

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the TECO F510 and is the answer not in the manual?

TECO F510 Specifications

General IconGeneral
Control ModeV/F Control, Sensorless Vector Control
Output Voltage3-phase 0 ~ Input voltage
Cooling MethodForced Air Cooling
Storage Temperature-20°C ~ +60°C
Enclosure RatingIP20
Input Voltage3-phase 380 ~ 480V
Output Frequency0~400Hz
Protection FunctionsOvercurrent, Overvoltage, Undervoltage
Braking UnitBuilt-in
CommunicationRS485, Modbus
Rated PowerVaries by model
Overload Capacity150% for 60 seconds
Operating Temperature-10 to 50°C
Humidity95% RH or less (non-condensing)
AltitudeUp to 1000m (derating above 1000m)