STEPS 18 THU 20: (Corner Fireplace)
If the chimney connection is to be made in the side of the fireplace, dry assemble the first corner
channel and mark the location of the flue hole on the designated surface. Mark a location for a
clean-out (soot) door on the opposite channel. Cut these holes in the outdoors.
Re-assemble the first two corner channels, using a little refractory on their bottom edges. Use a
tie down and 2 bands of packing tape or fiberglass-reinforced tape around each pair of channels -
so they do not fall during the next few steps.
Continue with the other four corner channels, using refractory mortar between them. Secure
each pair of channels with 2 bands of packing tape or fiberglass re-enforced tape as they are
installed.
Weights
#30C to 35C
130 lbs