Installation and Connections
Q9 Plus ASD Install/Op Manual
Start Up and Test
Before turning on the ASD ensure that:
The enclosure door is closed or reattached, and
secure.
R/L1, S/L2, and T/L3 are connected to the 3-
phase input power.
U/T1, V/T2, and W/T3 are connected to the
motor.
The 3-phase input voltage is within the specified
tolerance.
There are no shorts and all grounds are secure.
All personnel are at a safe distance away from the
motor and/or the motor-driven equipment.
DANGER