Plenum Installation
1. Assemble the plenum using the plenum’s
Installer Guide.
Airflow
7.3 Downflow Installation
Downflow installation must comply with national,
state, and local codes.
The air handlers are rated for zero clearance from
combustible materials.
STEP 1 - Prepare the location site as appropriate for
your application and per national, state, and local code
requirements.
STEP 2 - Set the unit in position.
Representative Illustration
Typical Downflow Installation
On units with sheet metal returns: Return plenum
must be flanged. Sheet metal drill point screws
must be 1/2” in length or shorter.
Typical Plenum Installation
Running change made. Air han-
dler was in upflow position so I
rotated it correctly 8/4/16.