EasyManua.ls Logo

Trane Sintesis RTAF SE - Page 4

Trane Sintesis RTAF SE
48 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
RLC-SVX19J_SHORT-GB
4
Pre-Installation
Installation Requirements
A list of the contractor responsibilities typically associated with the unit installation process is provided in Table 1.
Table 1
–
Installation requirements
Type
Trane Supplied
Trane Installed
Trane Supplied
Field Installed
Field Supplied
Field Installed
Foundation • Meet foundation requirements
Rigging
• Safety chains
• Clevis connectors
• Lifting beam
• Spreader bar
Isolation
• Elastomeric
isolators
(optional)
• Elastomeric isolators (optional)
Electrical
• Circuit breakers
(optional)
• Unit mounted
starter
• Circuit breakers (optional)
• Electrical connections to unit mounted starter
• Wiring sizes per submittal and NEC
• Terminal lugs
• Ground connection(s)
• BAS wiring (optional)
• Control voltage wiring
• Chilled water pump contactor and wiring
• Option relays and wiring
Water piping • Flow switch
• Taps for thermometers and gauges
• Thermometers
• Water fl ow pressure gauges
• Isolation and balancing valves in water piping
• Vents and drain
• Waterside pressure relief valves
• Water strainer
Insulation • Insulation • Insulation
Water Piping Connection Components • Grooved pipe
Other Materials
• R-134a, R-513A
or R1234ze
refrigerant
• Full factory
charge or pre-
load charge
• Dry nitrogen
(optional)
• Glycol for Glycol free confi guration
“Sintesis Model RTAF Installation
Completion Check Sheet and Request
for Trane Service”
Chiller Start-up Commissioning
(a)
• Trane, or an
agent of Trane
specifi cally
authorized to
perform start-
up of Trane
®
products
(a)
Start-up must be performed by Trane or an agent of Trane specifi cally authorized to perform start-up and warranty of Trane® products. Contractor
shall provide Trane (or an agent of Trane specifi cally authorized to perform start-up) with notice of the scheduled start-up at least two weeks prior to the
scheduled start-up.