Unit Start-Up
RT-SVX21N-EN 53
operating the unit in each of its Modes through all
available stages of cooling & heating), perform these final
checks before leaving the unit:
Program the Night Setback (NSB) panel (if applicable)
for proper unoccupied operation. Refer to the
programming instructions for the specific panel.
Verify that the Remote panel “System” selection
switch, “Fan” selection switch, and “Zone
Temperature settings for automatic operation are
correct.
Inspect the unit for misplaced tools, hardware, and
debris.
Verify that all exterior panels including the control
panel doors and condenser grilles are secured in place.
Close the main disconnect switch or circuit protector
switch that provides the supply power to the unit’s
terminal block or the unit mounted disconnect switch.

Table of Contents

Other manuals for Trane YSC072F

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Trane YSC072F and is the answer not in the manual?

Trane YSC072F Specifications

General IconGeneral
BrandTrane
ModelYSC072F
CategoryAir Conditioner
LanguageEnglish

Related product manuals