STEP
R
EQUIREMENT TO DO LIST ILLUSTRATION
4
If the oven is one of
the following models:
■ XEVC-2021-GPX
■ XAVC-2021-GPX
■ XAVC-16FS-GPX
5 Mandatory
Perform
the gas
analysis
test by
choosing:
GAS
FUMES
TEST 1
Enter the
Service Menu
4
type the PIN
99857
5
select UTILITIES
6
select
CALIBRA
TION
7
select GAS 1
FU
MES TEST.
The oven will start at
maximum speed of
the blower
SERVICE MENU
OVEN SETUP
ACCESSOIRES SETUP
HOOD SETUP
PROVER SETUP
SLOWTOP SETUP
DECKTOP SETUP
UTILITIES
5
UTILITIES
DEVICE INFO
LOAD MODEL PARAM.
UPDATE FIRMWARE
RESET TO FACTORY DEFAULT
CALIBRATION
6
CALIBRATION
GAS 2 FUMES TEST
GAS 1 FUMES TEST
7
1 2 3
4 5 6
7 8 9
. 0
OK
<-
SERVICE PIN
99857
3
4
PROGRAMSMIND.MAPSSET
CHEFUNOX
DATA
READY.COOK
CHEFTOP™
MULTI.TIME MISE.EN.PLACE
11:00
am 23/10/2014
READY
ROTOR.KLEAN
PROGRAMSMIND.MAPSSET
CHEFUNOX
ROTOR.KLEAN DDC STATS
READY.COOK
CHEFTOP MIND.Maps™ PLUS
MULTI.TIME MISE.EN.PLACE
23/10/2017
18:30
CHEFTOP
SLOWTOP
SETTINGS
USER SETTINGS
SERVICE MENU
NETWORK
1
2
6
Combustion analyzer
tool setting
Set the instrument for
measuring CO [ppm] and CO2
[% v/v].
Set the gas type among G20,
G25, G25.1 , G25.3 G110 (natur al
gas),
G30 (butane), G31 (propane).
Use [esc] to revert to the previous
parameter at any time.
Display/
param.
Explanation
Fuel
Selecting the area
version activates different
calculation formulas and
measurement parameters,
see Area versions.
■ Select the fuel: [ ] and [ ].
■ Sw
i
tch to the next param-
eter: [ ].
■ Exit the configuration
menu: [OK].
Unit of
pressure
■ Select the unit: [ ] and [ ].
■ Switch to the next param-
eter: [ ].
Unit of
tempara-
ture
■ Select the unit: [ ] and [ ].
■ Exit the configuration
menu: [OK].
Install the orifice and adjust the
throttle of the second gas valve
1.Switch the instrument on: Hold down
[ ], until all segments are shown on the
display.
2.Open “Measurements configuration
menu”: Press right function key [set].
3.Make settings:
Once the flue gas measurement
or ambient CO measurement is
configured, the gas sensors are zeroed
when the instrument is switched on
(zeroing phase). The flue gas probe
must be in the open air during the
zeroing phase!