COMMISSIONING
5. COMMISSIONING
Programming
The Controls
READ CAREFULLY
Verify the following points before putting the unit into
operation:
● The HRV is securely attached to the supporting
structure.
● The unit is closed correctly (ducts, etc.) and no
rotating or heating component is exposed to
human contact.
● The wiring is connected properly, including
grounding and protection against external
activation.
● All accessories are connected correctly.
● The condensation drain is properly connected to
the discharge piping and the drain is lled with
water.
● All connections comply with instructions in this
manual.
● No tools or other objects have been left inside
the unit as this could result in damage to the
unit.
ATTENTION!
●Anychangesormodicationstounitwiringare
prohibited and may void the warranty!
●Werecommendusingonlyaccessoriessupplied
by our company. If you have questions, please
contact Ventacity Systems.
READ CAREFULLY
●Read the entire commissioning section before
programming the HRV.
The control panel is provided with a touch sen-
sitive display–the unit is controlled by touching
symbols on the display.
5.1 ACTIVATION
Put the unit into operation (Stand-by) by turning the
main switch to position 1 (ON). When the main switch is
turned on, the control panel's display lights up and the
service data loads. The unit is ready to start once the
service data has loaded.
Activate
0
1