INSTALLATION
2-6
VersaPulse Select Service Manual
0621-499-01 12/95
®
®
13.) Confirm the power calibration.
Connect a good test fiber onto the fiber port and direct the fiber output towards the head of your
calibrated power meter, then, for each operating point, fire the system into the meter, confirming that
displayed power remains within ± 10% of the power indicated on the meter (typically, the power
calibration will be much more accurate than ±10%). If the power calibration is not better than ±10% at
all operating points, refer to Section 3 for instructions on system calibration.
14.) Check the fiber focus using a test fiber.
Two test fibers are shipped with the system. Check the fiber focus as described in Section 3, topic 3.2,
step 3.
15.) Replace all covers and prepare the system for demonstration to the customer.
16.) Demonstrate the system installation to the customer.
17.) (for U.S. Field Service) Fill out and mail the "self mailer" installation quality audit report.