Liebert® MC™
60-Hz Air-cooled MicrochannelCondenser
-Premium/EC Fan
Installer/User Guide

Table of Contents

Other manuals for Vertiv Liebert MCM080

Questions and Answers:

Vertiv Liebert MCM080 Specifications

General IconGeneral
BrandVertiv
ModelLiebert MCM080
CategoryHeat Pump
LanguageEnglish

Summary

Important Safety Guidelines

2 Site Preparation

2.1 Site Considerations

Provides essential guidelines for choosing an optimal installation location.

3 Inspection and Installation

3.6 Mounting the Condenser

Guidelines for securely mounting the condenser to the installation surface.

3.6.1 Standard Mounting Requirements

Specifies standard requirements for condenser mounting and anchoring.

3.6.2 Seismic-Certified and Wind-Certified Mounting Requirements

Details requirements for seismic and wind-certified mounting applications.

4 Electrical Connections

4.1 Line Voltage Wiring

Details on connecting the main power supply to the condenser unit.

4.2 Low-voltage Control Wiring—CANbus Communication and Interlock Connections

Guides for CANbus communication and interlock wiring between units.

4.2.1 Electrical Field Connection Descriptions

Describes specific electrical connection points and their functions.

5 Piping

5.1 Piping Guidelines

General guidelines for installing refrigerant piping, including brazing and material.

5.2 Field Piping Guidelines

Specific guidelines for field-installed refrigerant piping.

5.7 System Charging with Liebert MC

Detailed steps for charging the refrigerant system.

5.7.1 Liebert MC Charging, Units with Liebert Lee-Temp Receivers

Charging procedures for units with Liebert Lee-Temp receivers.

5.7.2 Liebert MC Condenser Charging with Liebert DSE Receivers

Charging procedures for units with Liebert DSE receivers.

6 Checklist for Completed Installation

6.2 Electrical

Checks electrical connections, wiring, and grounding for compliance and safety.

7 Initial Startup Checks and Commissioning

7.1 Startup Checklist

A pre-startup checklist to ensure all installation requirements are met.

7.2 Initial Startup

Step-by-step guide for the initial startup and operation of the condenser.

8 Troubleshooting

9 Control Operation

10 LIEBERT SEISMIC APPLICATION— OPTIONAL UNIT CONFIGURATION

10.1 Seismic Anchoring Considerations

Covers requirements for seismic anchoring, including hardware and load data.

11 SYSTEM MAINTENANCE

11.2 Condenser Cleaning

Instructions for cleaning the condenser coils to maintain efficiency.

12 PREVENTIVE MAINTENANCE CHECKLIST