16Liebert PCW - UM - 273895 - 04.10.2018
10 - Maintenance / Spare Parts
10.1 - Safety instructions
All maintenance operations must be carried out strictly observing the European and National accident prevention regulations.
We refer especially to the accident prevention regulations concerning electrical systems, refrigerators, and manufacturing resources.
Maintenance may be done to air conditioning equipment only by authorized and qualied technicians.
To keep all warranties valid the maintenance must adhere to the manufacturers regulations.
The work should be done in the system only when it is at standstill. Do this by switching o󰀨 the air conditioner at the
controller and the main switch. Post a warning sign saying: ”DO NOT SWITCH ON.”
Electrical components of device have to be switched o󰀨 and be checked that they are not under voltage.
Ignoring the safety instructions can be dangerous to persons as well as to the environment.
Soiled parts always cause a loss of performance and for switch or control devices can lead to the break- down of a plant.
10.2 - Spare parts
Only original spare parts made by Vertiv may be used. Using third- party material can invalidate the warrantee.
When making inquiries always refer to the ”Component List” supplied with the equipment and specify the model number, serial number
and, if available, the part number as well.
10.3 - Maintenance schedule
Monthly, quarterly, biannual and annual checks to be conducted according to the following guidelines.
All tasks and periods listed here are regulations from the manufacturer and need to be documented in an inspection report.
All these tas.ks should be carried out only by an authorized and trained technician. We recommend the Vertiv Cus-
tomer Service
10.4 - Air lter check and replacement
It is important to check the state of the air lter every month to maintain a good e󰀩ciency of air distribution through the evaporator coil.
CAUTION!
Sharp edges, splinters and exposed fasteners can cause personal injury! Only properly trained personnel wearing appropri-
ate safety headgear, gloves, shoes and glasses can carry out this operation!
DOWNFLOW UNITS
Top Filte r Brackets
Top Air Filters
Filter Bracket
Air Filter Air Filter
Air Filter Air Filter
1) Switch o the PCW unit and open
the front panel with the key.
NB : some components inside the
unit can be still at high temperature,
wait a few minutes before starting
the maintenance operation.
2) Unscrew two screws and remove
the lter brackets.
3) Remove air lters from the coils
starting from the upper lter, then
proceed with the lower lter.
4) Unscrew lobe handwheels and re-
move the top lter brackets.
5) Remove the top air lters.
1. Switch o󰀨 the PCW unit and open the front
panel with the key.
NB: some components inside the unit can be
still at high temperature, wait a few minutes
before starting the maintenance operation.
2. Unscrew two screws and remove the lter
brackets.
3. Remove air lters from the coils starting from
the upper lter, then proceed with the lower
lter.
4. Unscrew lobe handwheels and remove the
top lter brackets.
5. Remove the top air lters.