1. Lock the power disconnect switch in the “OFF” position. Be sure all electrical panels are closed
and securely latched.
2. Drain the center pivot supply line to a level below the frost line.
3. Remove the ush cap and Flex-Span supply hose. Make sure the low pressure drain valves
are working and that the center pivot is completely drained.
4. Disconnect poly line tubes from solenoid valves and end gun components to drain water from
lines.
5. All sprinkler control valves should be in the “open” position and drained. Valve control hoses
should be drained. Solenoid manifold assembly lters should be cleaned.
6. Protect moving parts and bearing surfaces against rust and corrosion by greasing all ttings.
7. Su󰀩cient oil should be drained from the center and wheel gearboxes to remove water and con-
taminants. Rell with manufacturers specied lubricant.
Section 1-24
Operation, Safety & Maintenance