YL9130 Column Compartment
Chapter 2. Installation
2-1. Inspection and site preparation
YL9130 column compartment is delivered along with the following parts when being shipped. Before
opening transportation package, perform inspection for trace of shock or mistake, and if there is
abnormality, do not open the contents and inform this company of it. And, if contents are opened, perform
inspection for existence of shock in the contents and contact with this company when trace of shock is
found.
The column compartment is a delicate instrument, so use original box and buffer material as far as
possible when re-packing it to transport instrument. If it is impossible to use original box; wrap pump with
several layers of buffer material, and fill the bottom, top and all other sides of pump with buffer material in
order to make pump endure shock or vibration during transportation.
Standard configuration of YL9130 column compartment
1) Main body of instrument
2) Power cord and fuse
3) Installation kit
4) Manual
Site requirement of YL9130 column compartment
1) Room with 20℃ temperature with variation ± 5℃ with and 60% humidity
2) Where no direct and straight sunlight
3) Plain floor without carpet
4) Where having spare space of 20cm or more
5) Where there are 10% or less voltage change, no frequency change and 100Ω or less grounding
point
6) Where there is no generation of corrosive gas and ventilation is well done
7) Where stable power of 110 or 220V is supplied
8) Where not receive electromagnetic induction from large transformer, high frequency heater, UPS,
etc.
9) Within 2500 m above sea level(storage within 4600m)
2