5 Operation of the FDM System
5.1 Set up the measuring System
For the commissioning of the FDM platform the suitable power supply, a USB cable type A-
A as well as the installation CD with the FDM application software are necessary. All com-
ponents are included in the scope of delivery of the FDM measuring system.
The underground of the set-up location must be plain and horizontal.
The platform must be set up on a slip-proof underlay or installed in a catwalk, so as
to exclude any danger to the test person caused by the platform sliding.
Do not set up the platform near a source of heating or in direct sunlight in front of a
window as a rise in temperature can lead to inaccurate measuring results.
Set-up the measuring system in a way, that the socket for the mains connection is
accessible easily at all times and that the device can be separated from the power
supply.
Once the measuring system is set up safely and horizontally, it can be connected to
the power supply and put into operation.
WARNING
5.2 How to switch the platform On/Off
The platform is switched on and off by software control as soon as the zebris FDM software
on the PC is started. If the device has been connected correctly, the green LED operating
indicator illuminates on the housing of the platform.