APPENDIX A: INITIAL SITE SURVEY CHECKLIST
Survey the areas where you have considered placing your new SLA system. Consider the following factors before you decide on
your ProX 800 facility.
8
Option 1
Option 2
Option 3
Option
1 2 3
Is there enough space for all equipment in that area, or will you separate the SLA system from the
secondary nishing equipment? (Refer to the section, “Optimal Site Layout” on page 3)
Is the ooring a solid, nonporous surface suitable for cleaning with isopropyl alcohol? (Refer to the
section, “Floor Area/Surface” on page 3)
Can the location be isolated, as a laser safety precaution? Can closing and locking the door during
installation or a service call prevent access to the location by unauthorized personnel? (Refer to the note
in the section, “Space Requirements” on page 3)
Can the required equipment and accessories be located either in the same room or in an adjoining
room to the ProX 800? (Refer to the section, “Optimal Site Layout” on page 3)
Is the air conditioning adequate for that area? (Refer to the section, “Temperature” on page 5)
Can humidity be maintained at an appropriate non-condensing level for the SLA material (20-50%)?
(Refer to the section, “Humidity” on page 5)
Is adequate electrical power available to the site? Are there at least two 220 V circuits; two outlets, each
with its own circuit and at least one additional 110/220 V outlet for servicing the system? (Refer to the
sections, “Electrical Requirements” on page 5 and “ProCure Electrical Requirements” on page 8)
Is there minimal UV-intensive lighting or natural sunlight? (Refer to the section, “Lighting” on page
7)
Is 10/100/1000 BASE-T Ethernet network and cabling installed to the location? (Refer to the section,
“Network Access” on page 7)
Is the room clean? Is construction of oors, ceilings, and walls complete? (Refer to the section, Air
Cleanliness” on page 7)
Is an appropriate forklift available during the installation appointment to move the system and its
accessories to their designated location? (Refer to the section, Availability for Adequate Forklift or
Lifting Equipment” on page 14)
Are the hallways and doorways adequate to allow passage of a forklift carrying a crated or uncrated SLA
system? (Refer to the section, “Minimum Passageway and Door Openings” on page 14)
ProCure UV Chamber?
Bench for cleaning parts?
Green part rinsing and nishing area?
Sink and eyewash station?
Is there a compressed air connection with pressure controller and fast-closing connection? (Optional)