Chapter 9 - Changing Thyristors in EXU ABB
9-2 (8) 3BHS202077 ZAB E01 Rev. C ACS 6000 Maintenance Manual
Figure 9-1 3-phase AC Power Controller
9.3.1 Preparatory Steps
1 Check that the drive has been deenergized and voltages have been
removed from the cabinet. See section
9.2 Safety
.
2 Cut off the cable tie securing the thyristor gate wires and remove them
from the pulse transformer.
3 Loosen the clamp bolts alternately until they can be turned by hand
and loosen the thyristor (see
Figure 9-2
). At first, do not open the bolts
completely to prevent the clamp from dropping.
Figure 9-2 Loosening the Bolts
9.3 Replacing Thyristors in EXUs for Brushless Excitation
Clamp