Installation and commissioning guide
1ZSC000563-AAF EN, REV. 4, 2021-06-23
8. Tighten the draw-rod nut (10).
NOTE!
Make sure that more than 10 mm of
the threads on the upper draw rod (35)
is remaining.
G006969
Torque
10 Nm
9.
Remove the bolts (6), washers (7) and lifting
tool (1).
G006956
10.
Remove the pull-through cord (12).
11.
Tighten the draw-rod nut, refer to Hydraulic tightening of the draw-rod nut, page 45.
End of instruction