Preparation
Safety
Read and follow all safety statements, warnings, and precautions in the Safety section of this
manual and manuals of all other equipment before installing, maintaining or repairing the
equipment.
Installation Tools and Hardware
You will need the following tools and hardware to install the BDFB:
• Material-handling equipment to unload the cabinet at the installation site, remove from
shipping container, and set in final position [minimum lifting capacity: 500 lbs. (227Kg)] Note:
Use the equipment weights and dimensions as a guideline for choosing material-handling
equipment.
• Digital multimeter (DMM) with 0.05% accuracy on dc scale
• Insulated hand tools
• Screwdrivers (flat-blade and Phillips)
• Wire cutters and stripper
• Crimp Tools
• Drill and Drill Bits to install floor anchors
• Torque wrenches 25-720 in-lb
• Sockets: 5/16”, 7/16”, 9/16”, 3/4”, 15/16”, 19mm
Installation