94 Product manual - PVS-175-TL;A.1 Version
EN
Commissioning procedure:
It’s highly recommended to connect the inverters in ethernet daisy chain (with or without ring) before
executing the commissioning procedure.
Make sure that all the inverter being commissioned features the last firmware version (the update can be
executed via Installer for Solar Inverters mobile APP).
The main steps to complete the commissioning procedures are listed below:
• Install the “Installer for Solar Inverters mobile APP” on mobile device.
• Login to the Aurora Vision installer account.
NOTE – D The account can be created in the mobile APP by following the dedicated wizard
procedure.
• Close the DC disconnect switches (19) to supply the inverter with input voltage from the photovoltaic
generator or close the AC switch downstream of the inverter (and AC disconnect switch (09) for the -S2,
-SX2 wiring box version) to supply the inverter with AC grid voltage. In the pre-commissioning phase the
“Alarm” LED keeps quickly flashing, “Power” and “GFI” LEDs are OFF.
ATTENTION – A This inverter can be powered both with AC or DC sources. In case of DC source
is used, make sure that irradiation is stable and adequate for the inverter commissioning
procedure to be completed.
• Manual claiming of the inverters:
The claiming process consists of indicating which inverters are
to be commissioned.
Claiming process can be executed by scanning the QR codes (J)
(printed on the Communication identification label) of all the
inverters being worked and putting the selected inverters into
the working list. Please insert in the list inverters belonging to
the same inverters family; no more than 40 inverters by time
can be configured together.
As an alternative of QR code scanning, claiming process can be
executed by selecting manually the SSIDs associated to the
Wi-Fi networks generated by each inverter to commission and
inserting Product key (I) when requested:
NOTE – D It’s required to digit also the dash “-” characters of the Product Key in the password
field.
SN WLAN: SSSSSSSSSS
PN WLAN: .V2PVKA 53.1
Mac Address:
AA:BB:CC:DD:EE:FF
PK: 0000 - 0000 - 0000- 0000
SN WLAN: SSSSSSSSSS
SN Wiring Box: ZZZZZZZZZZ
Remove and apply on the plant documentation
MAC: AA:BB:CC:DD:EE:FF
J
I