394 Chapter 11
Assembly Replacement Procedures
RF Input Connector
Replacement
1. Attach the new connector to the bracket. Torque to 80 inch pounds.
2. Replace the connector and bracket into the instrument.
3. Using the T-10 driver, replace the 2 screws that secure the input
connector bracket to the deck. Torque to 9 inch pounds.
4. Using a 5/16 inch wrench, reconnect the semi-rigid cable to the
connector. To avoid twisting the cable, hold onto it during tightening.
Torque to 10 inch pounds.
5. Replace the front frame. Refer to the “Front Frame” replacement
procedure.
6. Replace the instrument top brace. Refer to the “Top Brace”
replacement procedure.
7. Replace the instrument outer case. Refer to the “Instrument Outer
Case” removal procedure.