Rockwell Automation Publication 6000-IN006F-EN-P - March 2018 43
Drive Electrical Interconnection Chapter 3
Complete the Installation
1. Inspect the interior of all cabinets carefully for hardware or tools that may
have been misplaced.
2. Check and verify that no hardware or foreign material has fallen in the
secondary windings in the Isolation Transformer cabinet.
3. Check that all mechanical work has been completed properly. All barriers
and guards that may have been removed must be reinstalled.
4. Check that all electrical connections have been made and torqued as
specified.
5. Verify the safety circuit is working properly (see page 35
).
6. Reinstall all of the cabinet back plates.