Commissioning
Pre--commissioning inspections
L34--004EN/04
4/6
04--2004
E ALSTOM
Test operations
Test operations
D Theconnectionof auxiliarycircuits is sufficiently advancedto allowremote
controls to be used.
D Perform 5 CLOSING -- OPENING cycles electrically, by remote control.
OPERATION AUTHORIZED ONLY IF THE SF
6
PRESSURE GAS IS
GREATER THAN THE MINIMAL PRESSURE FOR THE INSULATION p
me
.
Caution
DUETO RISKOF DAMAGE TOCERAMICENVELOPES DURING TRANS-
PORTATION, PEOPLE PRESENT AT THE TEST OPERATIONS SHOULD
SHELTER THEMSELVES OR STAY AT A MINIMUM PROTECTION DIS-
TANCE (ABOUT 50 m).
VERY IMPORTANT
AFTER THE FIRST TEST OPERATION, IT IS FORBIDDEN TO REMOVE
THE OPERATING MECHANISM WITHOUT USING THE
BLOCKING
TOOL
(4).
NOTE
: To remove the operating mechanism, see in “Maintenance”,
the module “Replacing the operating device FK3 -- 1”.
4