INSTALLATION
Converge® Operator’s Manual MN-47239 Rev 3 5/23
40
How to Install the Oven on a Stand
Before you begin Make sure you have:
The appropriate stand for your oven
Regulation UL 197, 91.8
A pop rivet gun and rivets
An appropriate lifting device, and enough personnel, to safely move and position
the weight of the oven.
CMC-H2H: 304 lb (138 kg)
CMC-H3H: 394 lb (179 kg)
Procedure To install the ovens on a stand, do the following.
Step Action
1. Locate the front of the top panel.
2. Put the top upside down on a flat surface.
Continued on next page
VMC-TS-012917
H
W
C
X
X
FRONT
VMC-TS-012920