AUX DC Inverter Free Match 50HZ R32
159
◇ When draining multiple units into a common drain line, this common drain should be installed
about 100mm below each units drain outlet, as shown in the drawing.
◇ When finish installation please carry out the drainage test to ensure that the water flow
through the pipeline fluently, and carefully observe the junction to ensure that there is no water
leakage. If the unit is installed in the newly built house, strongly recommend that this test taken
before the ceiling installation. Even it is the heating only unit, this test is unavoidable.
4.5 Panel installation
As to the MB13 panel please refer to the following picture, the panel has four hooks which
attach to corresponding hangers on the unit and the panel should be positioned using these first.
The panel is then fixed into position by four bolts which are accessed through the four corner
panels on the grille.