Notes
Drainage pipe and connection piping should be wrapped by heat insulation material
respectively lift the air conditioner is proved my dew conditioner experiment. But if it keeps on
working in high humidity (the dew temperature is more than23℃) environment which may lead to
water leakage, please use following additional insulation material:
◇Glass fiber insulation material with the thickness between 10~20mm can be used.
◇The part of indoor unit which get in touch with the back side of ceiling should pasted with
insulation material.
◇Besides the previous more than 8mm thick insulation material, connection piping (both gas
pipe and liquid pipe), drainage pipe should be wrapped by additional 10~30 mm thick insulation
material.
Seal the hole on the wall.
◇To prevent rainwater or other foreign bodies from entering the room and air-conditioner, the
gap between wall hole and tubing, drain pipe and electric wire should be sealed with mastic,
sealant rubber or putty.
◇If the outdoor unit is higher than indoor unit, tubing should be bent to ensure that the lowest
point of the tubing is lower than the wall hole to prevent rainwater entering the room or
air-conditioner along the piping system.