3-8
3.3 Starting Operation
3.3.1 Pre-operation confirmation
Confirmation procedures
The configuration data confirmation procedure is shown below.
Check the following before starting operation.
The device is installed appropriately, and there is no damage or breakage to the
feedback lever, feedback pin, etc.
The air supply system has been completed and the appropriate supply air pressure
is being supplied (there are no air leaks).
The input signal (4 to 20 mA DC) is being applied.
(1) Operation confirmation procedure
The operation confirmation procedure for this device is shown below.
Step Procedure
1 Vary the input signal from the controller (constant-current supply) and confirm that the
position of the control valve changes according to the set characteristics. If the system
does not operate correctly, see “Troubleshooting.
2 After confirming proper operation, restore the electrical wiring to its original state and
tighten the terminal box cover firmly.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Azbil AVP201 and is the answer not in the manual?

Azbil AVP201 Specifications

General IconGeneral
BrandAzbil
ModelAVP201
CategoryValve Positioners
LanguageEnglish

Related product manuals