XPR-9 Series Two-Post Lifts 13 P/N 5900371 — Rev. D2 — May 2023
Installation Checklist
Following are the steps needed to install an XPR-9 Series Lift; perform them in this order.
☐ 1. Review the Safety Rules and information.
☐ 2. Plan for Electrical work.
☐ 3. Make sure you have the necessary Tools.
☐ 4. Review the Installation Orientation.
☐ 5. Review Clearances around and above the Lift.
☐ 6. Select the Installation Location.
☐ 7. Put Equalizing Cables into position in the Lift Posts.
☐ 8. Read about Hydraulic Contamination.
☐ 9. Read about Thread Sealant.
☐ 10. Put the Hydraulic Hoses into position in the Lift Posts.
☐ 11. Create Chalk Line Guides for the Posts.
☐ 12. Install the Equalizing Cables.
☐ 13. Install Cylinder Chain and Roller.
☐ 14. Anchoring the Posts and Install the Left and Right Foot Guards.
☐ 15. Install the Safety Assemblies and Safety Lock Cable.
☐ 16. Install and Connect the Hydraulic Hoses.
☐ 17. Mount the Power Unit (do not connect it to power yet).
☐ 18. Learn about Arm Restraint Gears.
☐ 19. Install the Lift Arms.
☐ 20. Contact the Electrician.
☐ 21. Connect the Power Unit (Electrician required).
☐ 22. Install the Power Disconnect Switch and Thermal Disconnect Switch (Electrician required).
☐ 23. Perform final Leveling.
☐ 24. Install the Safety Covers.
☐ 25. Lubricate the Lift.
☐ 26. Perform an Operational Test.
☐ 27. Review the final Checklist.
☐ 28. Leave the Manual with the Owner/Operator.