Selecting a Location
When selecting the location for your Lift, consider:
Architectural plans. Consult the architectural plans for the desired location. Make sure there
are no contradictions between what you want to do and what the plans show.
Available space. Make sure there is enough space for the Lift: front, back, sides, and above.
Refer to Specifications for exact measurements.
Overhead obstructions. Check for overhead obstructions such as building supports, heaters,
lights, electrical lines, low ceilings, and so on.
Power. An appropriate electrical power source for the Lift’s Power Unit is required.
Outdoor installations. Your Lift is approved for indoor installation and use only. Outdoor
installation is prohibited.
Do not install the Lift on any surface other than Concrete conforming to the minimum compressive
strength, aging, reinforcement, and thickness stated in these requirements.
Never install the Lift over a concrete expansion joint.
All Anchors must be a minimum of 6 in. (152 mm) away from any expansion seams, control joints
or other inconsistencies in the Concrete.
Never install the Lift on hand-mixed Concrete.
Do not install the Lift on a secondary floor level or on any ground floor with a basement beneath
without written authorization from the building Architect and prior approval of BendPak Inc.
Never drill or cut into a post tensioned slab. Seek qualified personnel to identify cable locations
prior to cutting or drilling
WARNING Installing your Lift on a surface with more than three degrees of slope could lead to
injury or even death. Only install your Lift on a level floor (defined as no more than
3/8 of an inch difference over the installation area). If your floor is not level, consider
making the floor level or using a different location.
Concrete specifications XPR-9TF and XPR-9SBT. Verify the concrete is at least 4.25
inches thick, 3,000 PSI, and cured for a minimum of 28 days. Do not install the Lift on cracked or
defective concrete. Anchor Bolts must be more than 6 inches from cracks in the concrete or from
a wall.
CAUTION BendPak Lifts are supplied with installation instructions and concrete anchors that
meet the criteria set by the latest version of the American National Standard
“Automotive Lifts – Safety Requirements for Construction, Testing, and Validation,”
ANSI/ALI ALCTV. Consult with an expert for any special regional structural and/or
seismic anchoring requirements specified by any other agencies and/or codes such
as the Uniform Building Code (UBC) and/or International Building Code (IBC).
Check your floor for the possibility of it being a post-tension slab. In this case, contact the building
architect before drilling. Using ground penetrating radar may help you find tensioned steel.
WARNING Cutting through a tensioned cable can result in injury or death. Do not drill into a
post-tension slab unless the building architect confirms you are not going to hit
tensioned steel, or you have located it using ground penetrating radar. If colored
sheath comes up during drilling, stop drilling immediately.

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the BendPak XPR-9 Series and is the answer not in the manual?

BendPak XPR-9 Series Specifications

General IconGeneral
BrandBendPak
ModelXPR-9 Series
CategoryLifting Systems
LanguageEnglish

Related product manuals