Connecting the Hydraulic Hoses
Some of the Hydraulic Lines were put into place much earlier in
the installation. It is now time to finish routing and installing them.
This section covers connecting the Elbow Fitting that connects to
the Power Unit.
The following procedure assumes the Hydraulic Lines were put
into position earlier in the installation. Refer to Routing
Hydraulic Lines for more information. If they were not put into
position earlier, you must do so now, before beginning the
following procedure.
To finish connecting the Hydraulic Lines:
1. Locate the Short Hydraulic Line and the remaining Elbow Hydraulic Fitting.
2. On the Power Unit, locate a hydraulic pressure out port on the Power Unit (labeled P, P1, or
P2), remove the shipping plug. Place a few drops of hydraulic fluid on the O-Ring of the Elbow
Hydraulic Fitting (06 ORB to 06 JIC) and install in the P1 or P2 port of the Power Unit.
3. The figure below shows locations of the Hydraulic Pressure Ports on the Power Units that are
available for the XPR-9 Series of Lifts.
4. Connect the Hydraulic Hose to the Elbow just installed.