Biodom C15 | instructions for use, maintenance and installation | February 2019
19
required documentation in accordance with standards in force;
perform training of customer for operation and regular maintenance and cleaning of the
device.
INSTALLATION
Responsibility for installation work in the space is entirely upon the customer.
Before proceeding with installation, the installer must comply with all required legal safety standards,
especially:
check that norms regarding pellet boiler installation meet local, national and European norms;
heed to requirements set forth in this document;
check that pipes and air intake are compliant with the type of installation;
do not make temporary electrical connections by using unsuitable cables;
check earthing of electrical system;
always use individual safety equipment and all legally required protection;
always allow sufficient space for maintenance work;
acquire consent of chimney sweep for connection of boiler to flue;
perform measurement of smoke gases outlet after finished installation.
6.1. PLACEMENT
It is advisable to remove pellet boiler packaging only when it is in the place of installation.
If the adjacent walls and/or flooring are made of material that is not heat resistant, suitable protection
must be provided using insulating, non-combustible material.
For protection of flooring, made of flammable material, we advise installing a metal plate with
thickness 3 to 4 mm under the boiler, which protrudes at least 30 cm out from the front of the pellet
boiler.
Pellet boiler must be installed in accordance with drawing that defines distances from walls (figure 1).