36 / 52
8.0 MAINTENANCE
Maintenance and replacement work must be carried out by expert maintenance technicians
trained in the observance of applicable laws on health and safety at work and the special
ambient problems attendant on the installation.
Before doing any work on the unit, the operator must rst switch off power to the gear unit
and ensure that it is out of service, as well as taking all necessary precautions against it
being accidentally switched on again or its parts moving without warning (due to suspend-
ed loads or similar external factors).
Furthermore, all additional environmental safety precautions must be taken (e.g. elimina-
tion of residual gas or dust, etc).
• Before doing any maintenance work, activate all the safety devices provided and, if necessary,
inform persons working in the vicinity. Cordon off the area around the unit and prevent access to
any equipment which, if activated, might be the cause of unexpected health and safety hazard.
• Replace worn components with original spare parts.
• Use the lubricants (oil and grease) recommended by the Manufacturer.
• When working on the gear unit always replace all gaskets and seals with original new ones.
• If a bearing requires replacement, it is good practice to also replace the other bearing supporting
the same shaft.
• We recommend replacing the lubricating oil after all maintenance work.
The above instructions are aimed at ensuring efcient and safe operation of the gear unit.
The Manufacturer declines all liability for injury to persons and damage to components due to the
use of non-original spare parts and non-routine work that modies the safety requirements without
the Manufacturer’s express prior authorisation.
Refer to the specic spare parts catalogue when ordering spare parts for the gear unit.
Do not dump polluting liquids, worn parts and maintenance waste into the environment.
Dispose of all such materials as specied by applicable legislation.
• Observe the routine inspection and maintenance schedule to ensure the unit’s correct operation
and the effectiveness of the explosion protection.
• Always apply fresh Loctite 510 or other product with similar properties and application range to
all disassembled threads.
• Before servicing or repairing internal components, allow the gear unit to cool down completely
before opening the casing so as to avoid burns from parts which are still hot.
• On completion of maintenance work, make sure that all safety measures and equipment have
been applied and reset.
• Clean the gear unit thoroughly after maintenance and repair work.
• On completion of maintenance, tighten all vent, ller and level plugs to their specied torques
(chart A1).
• On completion of any maintenance work all seals must be retted and sealed as prescribed.
• Regardless of the type of gear unit, whenever a seal ring is replaced its lips should be smeared
with a thin layer of grease (Fluorocarbon gel 880 ITP or other product with similar properties and
application range) before assembly.
• Use only original spare parts for repairs.