4. Position a cable so that the key (the ridge on one side of the cable connector) is aligned with the slot in the transceiver.
Insert the cable into the transceiver until the latching mechanism clicks.
Cables are keyed so that they can be inserted in only one way. If a cable does not slide in easily, ensure that it is
correctly oriented.
Verifying the Operation of New Transceivers
You can use the following commands to verify if the transceivers are working correctly:
errDump
fabricShow
sfpShow
switchShow
Refer to the Brocade Fabric OS Command Reference Manual for output examples and descriptions.