SECTION 8
HANDLING, SERVICE AND MAINTENANCE
CESSNA INSPECTION PROGRAMS
CESSNA
MODEL 172S NAV
III
In
lieu of the 100 hour and annual inspection requirements,
an
airplane may be inspected
in
accordance with a Progressive Care
Inspection Program or a PhaseCard Inspection Program. Both
programs offer systems which
allow the work load to be divided into
smaller operations that can
be
accomplished
in
shorter time
periods.
The Cessna Progressive
Care Inspection Program allows
an
airplane to be inspected
and
maintained
in
four operations. The four
operations are
recycled each 200 hours
and
are recorded
in
a
specially provided Aircraft Inspection
Log
as each operation
is
conducted.
The PhaseCard
Inspection Program offers a parallel system for
high-utilization
flight operations (approximately 600 flight hours per
year). This system utilizes
50
hour intervals (Phase 1 and Phase 2)
to inspect high-usage systems and components.
At
12
months or
600 flight hours, whichever occurs first, the airplane undergoes a
complete (Phase 3) inspection.
Regardless
of
the inspection method selected, the owner should
keep
in
mind that
FAR
Part 43 and
FAR
Part
91
establishes the
requirement that
properly certified agencies or personnel
accomplish all required F
AA
inspections
and
most of the
manufacturer recommended inspections.
8-8
U.S.
172SPHAUS-00

Table of Contents

Other manuals for Cessna 172S Nav III

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Cessna 172S Nav III and is the answer not in the manual?

Cessna 172S Nav III Specifications

General IconGeneral
BrandCessna
Model172S Nav III
CategoryAircrafts
LanguageEnglish

Related product manuals