7. Test the operation of the rotary slide by pulling on the ends of
the rope. Be sure the outlet drop is centered over the outlet
hole, then move the rotary slide to the open position (check by
looking up through the drop opening) and mark the short end of
the rope where it goes through the guide hole.
Tie a knot in the rope at the marked spot to act as a stop for the
rotary slide.
8. Install green and red indicator balls on the ends of the rope. Tie
knots in the rope to hold the balls in place. Use the green ball
on the rope used to open the outlet drop. Use the red ball on
the rope used to close the drop. This will indicate if the Outlet
Drop is open or closed.
9. Dab PVC cement around the auger tube to prevent the drop from
shifting on the tube.
10. Two screws are supplied for use in the bottom of the drop to
attach a drop tube to the system.
Figure 5. Model 108 Outlet Drop Assembly.
Key Description
1 Insert (For Steel or PVC System)
2 Top Half
3 Rope
4 Rotary Slide
5 Bottom Half w/Spout

Other manuals for Chore-Time FLEX-AUGER 108

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Chore-Time FLEX-AUGER 108 and is the answer not in the manual?

Chore-Time FLEX-AUGER 108 Specifications

General IconGeneral
BrandChore-Time
ModelFLEX-AUGER 108
CategoryIndustrial Equipment
LanguageEnglish