7 Start-up
7.1 General description
The indicated operations should be done by qualied technician with specic training on the product.
Upon request, the service centres performing the start-up.
The electrical, water connections and the other system works are by the installer.
Agree upon in advance the star-up data with the service centre.
Before checking, please verify the following:
the unit should be installed properly and in conformity with this manual
the electrical power supply line should be isolated at the beginning
the unit isolator is open, locked and equipped with the suitable warning
make sure no tension is present
After turning o the power, wait at least 5 minutes before accessing to the electrical panel or any other electrical component.
Before accessing check with a multimeter that there are no residual stresses.
7.2 Preliminary checks
For details refer to the dierent manual sections.
Unit OFF power supply
1. safety access
2. functional spaces
3. air ow: correct return and supply (no bypass, no stratication)
4. structure integrity
5. fans run freely
6. unit on vibration isolators
7. unit input water lter + shut-o valves for cleaning
8. vibration isolators on water connections
9. expansion tank (indicative volume = 5% system content)
10. cleaned system
11. loaded system + possible glycol solution + corrosion inhibitor
12. system under pressure
13. vented system
14. refrigerant circuit visual check
15. earthing connection
16. power supply features
17. electrical connections provided by the customer
7.3 Start-up sequence
For details refer to the dierent manual sections.
Unit ON power supply
1. compressor crankcase heaters operating at least since 8 hours
2. o-load voltage measure
3. phase sequence check (unit only 400/3/50)
4. unit ON
5. load voltage measure and absorptions
6. check all fan operating
7. measure of return and supply water temperature and ow valutation
8. super-heating and sub-cooling measure and discharge temperature
9. check no anomalous vibrations are present
10. climatic curve personalization
11. set date and time
12. personalise scheduling
13. climatic curve personalization
14. set remote control *
15. complete and available unit documentation
*If present

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the CLIVET WSAT-XIN Series and is the answer not in the manual?

CLIVET WSAT-XIN Series Specifications

General IconGeneral
BrandCLIVET
ModelWSAT-XIN Series
CategoryChiller
LanguageEnglish

Related product manuals