Functional Test, on Ground
98-145168-A Chapter 6: Verification 6-3
6666
6.3 Functional Test, on Ground
6.3.1 Before you start
The system must be activated before performing this test. For further details see Activation
of airtime services on page 5-49.
6.3.2 Check list for functional test on ground
The following list provides some of the most important checks to perform after power-up,
but other additional checks may be relevant for the specific installation.
If you already know that certain interfaces or services are not going to be used, it is not
necessary to perform tests on these specific interfaces or services.
Item Description of Check Reference
Value/
Comment
CSDU LEDs Check that the Power LED is
green
Check that the Fail/Pass LED is
green
Check that the Logon LED is
green
MCDU
headsets #1 to
#3
Make an aircraft to ground call AVIATOR 200S
User Manual
Make a ground to aircraft call AVIATOR 200S
User Manual
Ethernet Connect to the Internet from a
laptop, using the Ethernet AISD 1
/ EFB 1 connection. .
AVIATOR 200S
User Manual
ACARS / AFIS /
CMU
Send a test message and verify
the reply or request for weather
data and verify the data is
downloaded. Both is done from
the CDU / MCDU.
CDU / MCDU
Manual
Table 6-2: Check Sheet: Functional test, on Ground