Inteli NT GeCon MINT, SW Version 1.4, ©ComAp – June 2007
IGS-NT-GeCon-MINT-1.4.PDF
8
GCB closing from controller can be blocked by BI: GCB disable.
AUT mode
Engine start or Power management is activated from GeCon BI: Sys start/stop
GeCon BI: ReadyToLoad initiates GeCon “Running” state” - activates Gener protect: Min stab time a Max
stab time within the generator electric protections are activated.
Gen-set starts synchronizing and is loaded/unloaded automatically based on
o Power management setting
o GeCon BI: Sys start/stop
GeCon will stop engine started from MCU when BI Sys start/stop or due to Power management function.
Power management
Automatic gen-set start / stop function based on load changes and/or Running hours or Engine size.
Following functions are available:
Power management in kW
Guarantees adjustable load reserve (load step) in kW. Suitable for load demand-based optimization.
Activation: #Pwr mgmt mode = ABS (kW)
Power management in kVA
Guarantees adjustable load reserve (load step) in kVA. Suitable for generator- or busbar dimensioning-
based optimization.
Activation: #Pwr mgmt mode = ABS (kVA)