4.3 Commissioning Steps
Complete the checklist above before commissioning the inverter as follows:
1.) Turn on the AC circuit breaker.
2.) Turn on the DC circuit breaker. (Skip these two steps if there are no
circuit breakers.)
3.) Switch the DC Switch to the “ON” position. When the energy
supplied by the PV array is sufficient, the LED of inverter will light up.
The inverter will then start up.
4.4 Connection to the inverter – Wireless
Once powered, the inverter will automatically create a wireless network
that will be visible as an Access Point from the user devices (tablet,
smartphone, etc.), connection to the inverter via Wi-Fi .
1.) Open the CPS Connect Pro app and select No-LCD Inverter.
2.) Enable the wireless connection on the device which is being used for
the board setup (tablet or smartphone) and connect it to the Access
Point created by the inverter system: the name of the wireless
network created by the system that the connection should be
established with, will be: CPLK-XXXXXXX where “X” can be found
on the “LinKIT Label” placed on the side of the WiFi module.
3.) Please input the password “Password”(Capital P)
4.) Touch the Setting icon and input the password “1111” to access the
Settings interface.
5.) Select the Inverter Parameters tab to set the Grid Code, PV Link
Type, Neutral Line, RS485 and Inverter Clock” as shown in Figure 4-
1.