55
Grid Code: 3 Standard codes are available – IEEE1547,
Rule21, ISO-NE. Other SRDs can be implemented
by manual configuration of settings.
PV Link Type: (N/A – 1 MPPT)
Neutral Line Setting: Select if a neutral is connect or not
RS485: Choose the communication data Modbus Address
and Baud Rate (9600). Each Inverter on a daisy
chain must have a unique Modbus Address.
Inverter Clock: Set the system clock
When the device screen shows the normal operation status (Figure
4-2) and the “RUN” light on the LED panel is illuminated, this is an
indication that the grid connection and power generation are successful.
INSTRUCTION:
Please check with your local electricity supply company before
selecting a grid standard. If the inverter is operated with a wrong grid
standard, the electricity supply company may cancel the
interconnection agreement. Placing the inverter into operation before
the overall system complies with the national rules and safety
regulations of the application is not permitted.