Conduit Installation
7
4 Conduit Installation
Getting Started
The signal and DC power conduit that interconnects the power and control cabinet
or the power cabinet to the LED panels must be made of steel EMT, RMC, IMC-type
conduit.
Note: All DDMS components must be installed before installing conduit and power
and signal cables.
The size of conduit routing from the DDMS cabinet(s) varies depending on the number of
LED panels in the set. The contractor may choose which type of conduit material to use
unless DC power is in use.
AC Power Conduit
The contractor may choose which type of conduit material to use.
DC Power Conduit
Contact Daktronics for information on which size conduit is needed.
Signal Conduit
The contractor may choose which type of conduit material to use.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Daktronics VM-1020 Series and is the answer not in the manual?

Daktronics VM-1020 Series Specifications

General IconGeneral
BrandDaktronics
ModelVM-1020 Series
CategorySports & Outdoors
LanguageEnglish

Related product manuals