Follow all the instructions described
below with the help of picture 1:
• Open the water tap 1 and make
sure that there is no leaking hose
connection.
• Turn on the electrical switch 7 and
turn the knob 2 clockwise. Make
sure the display turns on.
• Once the machine is on, the automatic
level starts lling up the boiler until
the proper level is reached. At this
stage, the symbol blinks on the
display.
• After the lling phase, the group heads
start heating. The set temperature
value blinks on the display.
• After the heating phase, the
temperature values stop blinking
and the set value for each group is
shown.
• Straight afterwards, the boiler starts
to heat up and its set temperature
value blinks on the display.
• During this phase, the brewing groups
can be used.
• When the boiler reaches the correct
temperature, the set value stops
blinking and the unit will emit 2 bleeps
conrming the machine is ready for
use.
WARNING:
The heating sequence starts only
when the Timer is deactivated and
the machine is turned on after it has
been completely switched o through
the main switch 2. This sequence
is conceived in order to save a good
quantity of energy during the heating
up of the machine, thus avoiding
problems of local electrical system
overloading.
starting the machine -> pic. 1