9 Commisioning
Before commissioning the system, first check the following items:
Correct installation of piping, wiring, and ducts
Efficient drainpipe open to air
Appropriate insulation protection
Correct earthing
Correct power supply
No obstacle outside/or inside the air inlet or outlet
No air in the water piping and all shut-off valves opened
Sufficient inlet water pressure (≥1.5 bar)
To commision this unit, follow the steps below:
Caution! Operation without water in water
tank may result in damage of auxiliary e-
heater. Due to such damage, the warranty is
not valid.
Caution! Water temperatures over 50°C can
cause severe, or even fatal, scalding injuries.
Caution! If the unit is used for the first time or used again after emptying the tank, make sure that the tank
is filled with water before turning on the power.
To fill the tank with water:
1
2
3
1. Open the cool water inlet (1) and hot water outlet (2).
2. When water flows out from the water outlet, the tank is full.
3. Turn off the hot water valve (3).
Start the unit, set the operational mode and temperature settings as described in Operating instructions, Page 1.
Installation, Service and User Manual VMGFK202 – 19

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Danfoss DTW 300 SP and is the answer not in the manual?

Danfoss DTW 300 SP Specifications

General IconGeneral
BrandDanfoss
ModelDTW 300 SP
CategoryIndustrial Equipment
LanguageEnglish

Related product manuals