1.4 Overlapping Bi-Parting Gate Operator Positions
Secondary
Operator
Position
Gates Opening Inside
Primary
Operator
Position
All loop detector, safety and access control devices are
wired to the PRIMARY operator.
AC power is also wired to the primary operator ONLY.
This gate MUST open
first in this example.
Overlap
IMPORTANT
Interconnection Cable
See page 19.
When installing overlapping gates (using a maglock to secure gates in the center or architectural overlapping design etc.),
certain considerations must be taken into account or gates will NOT operate correctly.
The SECONDARY operator OPENS 1.5 secs BEFORE the primary operator (SW2, switch 1 - ON) to allow the secondary
operator’s gate to stay clear of the gate overlap. It is VERY important to install the SECONDARY operator on the gate that opens
FIRST according to YOUR specific gate layout or gates will NOT operate correctly.
The distance EACH gate travels while cycling
MUST be set the same (Limit sensors settings),
otherwise the 1.5 second time delay may NOT
allow the primary operator’s gate with the overlap
to CLOSE BEFORE the secondary operator’s gate.
IMPORTANT
The SECONDARY operator
MUST be installed on the
gate that opens FIRST.
IMPORTANT