The valve proving function can be enabled or disabled in parameterisation
mode.
After a power failure or a fault unlock, the gas valves are always subjected to
a leakage check before the burner is started. Otherwise, a leakage check is
always performed after a controlled shut-down of the burner.
Only a gas pressure switch is used to check the gas valves for leaks and
monitor the minimum gas pressure. The gas pressure switch must be con-
nected in the circuit between valve Y2 and valve Y3. A leakage check can thus
be performed without the need for additional devices.
A separate gas pressure switch (GW_VPS) is required to test the gas valves for
leaks. The gas pressure switch must be connected in the circuit between valve
Y2 and valve Y3.
After a controlled shut-down, valve Y3 is closed after a 2-second delay. The
external valve remains open. The test section is thus rendered pressureless.
The gas pressure switch must have switched off (open). Test period V1 for the
first valve (Y2) on the gas side now commences.
During the test period, a pressure sufficient to activate the gas pressure switch
must not build up inside the test section, otherwise a fault shut-down will take
place and the fault code for valve 1 leaky displayed.
At the end of test period V1, valve Y2 is opened for 1 s. The gas pressure switch
must switch over within this period of time and indicate the presence of gas
pressure, otherwise all valves are closed and the gas fail-safe program is
executed.
Once the period of time has elapsed, valve Y2 and the external pilot valve are
closed.
During the test period for valve Y3, a pressure drop below the operating point
of the preset minimum gas pressure must not occur, otherwise a fault shut-
down will take place and the fault code for valve 2 leaky displayed.
- The volume of gas trapped in between valve Y2 and valve Y3
- The preset pressure switching points
- The gas mains pressure applied
- The permissible leakage rate
Integrated valve proving
system, electronic modu-
lation
Valve test, gas burner
Gas burner, electronic modula-
tion
Gas burner, pneumatic modula-
tion
Functional sequence
Test times for valve Y2 and valve
Y3 are derived from:

Table of Contents

Other manuals for Dungs MPA22

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Dungs MPA22 and is the answer not in the manual?

Dungs MPA22 Specifications

General IconGeneral
BrandDungs
ModelMPA22
CategoryController
LanguageEnglish

Related product manuals