- 6 -
4. Operation
4.1 Standard Operation
Prior to operating the machine, please confirm that
1. The proper voltage is being supplied to the motor
2. All fasteners and protective covers are securely in place
3. All electronic components are dry
Machine Operation
1. Plug the machine into the power source
a. DO NOT hard wire the machine to the power source
2. Turn on air supply.
3. Feed cartons to be erected into storage tray
4.2 Case Erection
1. Adjust the machine for the size of the cartons to be erected.
2. Place the cartons on the carton storage shelf.
3. Machine will place carton, fold front and rear lower flaps, fold left and right lower flaps, and seal
bottom of the carton.