OPERATION
Eaton
®
9140 (9910-E82/E83) UPS Installation Guide for IBM
®
Applications S 164201715 Rev 2
www.eaton.com/ibm
52
Configuring the UPS for EBMs
To ensure maximum battery runtime, configure the UPS for the correct
number of EBMs:
1. Select MENU from the system status screen, then select SETUP,
USER SETUP, and BATTERY PACK.
2. Use the
or button to select the number of battery packs in
your UPS configuration:
All UPS and EBM Cabinets
Number of Battery Packs
UPS + 1 EBM 2
UPS + 2 EBMs 3
UPS + 3 EBMs 4
UPS + 4 EBMs 5
3. Press the button to save the setting.
4. Press the
button until the system status screen appears.
Initiating the Battery Test
NOTE The batteries must be fully charged and the UPS must not be in Battery mode to
perform the battery test.
NOTE For an accurate battery test, test the UPS with at least 10% load applied to the UPS.
You can configure the battery test settings, initiate a test, cancel a test,
and view the test report.
Configuring the Battery Test. The UPS automatically performs a battery
test approximately every 90 days if this option is enabled. To enable or
disable the automatic battery test, select MENU from the system status
screen, then select SETUP, USER SETUP, and BATTERY TEST. Select
to enable or disable the automatic test.