Eaton 93PM UPS 480V Three-Wire – 100 kW Frame Installation and Operation Manual 164000227—Rev 07 15
Table 1. Air Conditioning or Ventilation Requirements During Full Load Operation
Model
UPS
Rating
Input/Output
Voltage
Heat Rejection
BTU/hr x1000 (kg-cal/
hr)
Minimum Required
Cooling
Air Flow
Eaton 93PM-100-1
Eaton 93PM-100-2 (N+1)
20 kW
480/480 2.55 (643)
378 liter/sec
(800 cfm)
Eaton 93PM-100-1
Eaton 93PM-100-2 (N+1)
30 kW
480/480 3.58 (903)
Eaton 93PM-100-1
Eaton 93PM-100-2 (N+1)
40 kW
480/480 4.56 (1150)
Eaton 93PM-100-1
Eaton 93PM-100-2 (N+1)
50 kW
480/480 5.70 (1438)
Eaton 93PM-100-2
Eaton 93PM-100-3 (N+1)
60 kW
480/480 7.16 (1807)
Eaton 93PM-100-2
Eaton 93PM-100-3 (N+1)
70 kW
480/480 8.36 (2108)
Eaton 93PM-100-2
Eaton 93PM-100-3 (N+1)
80 kW
480/480 9.12 (2300)
Eaton 93PM-100-2
Eaton 93PM-100-3 (N+1)
90 kW
480/480 10.26 (2588)
Eaton 93PM-100-2
Eaton 93PM-100-3 (N+1)
100 kW
480/480 11.40 (2875)
The UPS equipment operating environment must meet the weight requirements shown in Table 2 and the size
requirements shown in Figure 3 through Figure 10. Dimensions are in millimeters (inches).
NOTE Refer to the Eaton 93PM Sidecar Integrated Accessory Cabinet-Tie and Tie Bypass (50
kW and 100 kW SIAC-T, and 50 kW and 100 kW SIAC-TB) Installation and Operation
Manual, listed in paragraph 1.8 For More Information, for Sidecar Integrated Accessory
Cabinet-Tie (SIAC-T) and Sidecar Integrated Accessory Cabinet-Tie Bypass (SIAC-TB)
weight and size requirements.
UPS Installation Plan and Unpacking