UPS System Installation
Eaton 9E UPS (40–60 kVA, 208/220V) Installation and Operation Manual P-164000058—Rev 4 www.eaton.com/powerquality 4-25
6. Repeat Step 3 through Step 5 for each battery shelf (see Figure 4-23) to complete the battery string
connections.
7. Reinstall the internal safety shield panel removed in Step 2.
8. Close the outside door and secure the latch.
Figure 4-22. Battery Location
NOTE The Eaton 9E-40 model has battery strings installed on three shelves. The Eaton
9E–60/40 and Eaton 9E–60/60 models have battery strings installed on four shelves.
(Batteries are located behind
safety shield.)
Bottom Internal Safety Shield Panel