EasyManua.ls Logo

Eaton 9E - Figure 6-8. Maintenance Bypass Interlock Cover

Eaton 9E
114 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
UPS Operating Instructions
Eaton 9E UPS (40–60 kVA, 208/220V) Installation and Operation Manual P-164000058—Rev 4 www.eaton.com/powerquality 6-15
5. Slide the interlock cover to the right (see Figure 6-8).
6. Open the maintenance bypass breaker.
7. Transfer the load to normal by performing the procedure in paragraph or 6.3.4.
Figure 6-8. Maintenance Bypass Interlock Cover
6.3.9 UPS and Critical Load Shutdown
To perform maintenance or service on the critical load, shut down power to the load:
1. Turn off all equipment that is being powered by the UPS.
2. Perform the LOAD OFF procedure in paragraph 6.3.12.
The output and bypass backfeed relays open, and the power module is turned off.
3. Perform the battery charger off procedure in paragraph 6.3.10.
The input and battery relays open.
WARNING
Power is present inside the UPS cabinet after the upstream input feeder circuit breakers are
opened because of the installed internal batteries.
Maintenance Bypass
Breaker
Output Breaker
Interlock Cover

Table of Contents

Related product manuals