Eaton Power Xpert 9395 UPS Installation and Operation Manual 164201725—Rev 15 109
5. Reinstall the conduit landing plate.
6. Install conduit between the UPS and SCM II. See Figure 70 for SCM II knockout hole location.
7. Install wiring between the UPS and SCM II. See Figure 58 and Table 25 for the Powerware Hot Sync CAN
Bridge Card terminal location and wiring information, and Figure 66, Figure 64, and Table 29 for the SCM II
terminal location and wiring information.
NOTE 120 Vac for the SCM II should be supplied from the critical bus by facility planners or the
customer.
8. Install 120 Vac power wiring from the critical bus to the SCM II. See Figure 66, Figure 64, and Table 29 for
the terminal location and wiring information.
Figure 66. Supervisory Contact Module II Terminal Location.
Ground
Terminal
Terminal TB1 Signal
Connections from the UPS
Terminal TB3
120 Vac Power
Terminal TB2 Customer
Supervisory Contact Interface
NOTE Setup of the Powerware Hot Sync CAN Bridge Card must be performed by an
authorized Eaton Customer Service Engineer. Contact an Eaton service representative
to schedule a date.
9. Install wiring between the SCM II terminal block TB2 and the monitoring equipment. See Figure 66 for
terminal block location and Figure 67 for terminal assignments.
10. Close the front door and secure the latch.
11. Restart the UPS. See Chapter 7 UPS Operating Instructions for startup instructions.
Installing Options and Accessories